Internal Re-planning
Internal Re-planning covers any budget change made without a contractual scope change: moving budget between Control Accounts, re-time-phasing work, converting Planning Packages into Work Packages, rolling wave planning, de-scoping effort, distributing Management Reserve into Control Accounts, and rate changes that affect Budget at Completion. The controlling test is the ceiling — so long as the sum of all Control Account budgets stays within the Contract Budget Base, or within the Total Allocated Budget once Management Reserve is counted, the change is internal re-planning. It is a normal, ongoing part of managing a project. Formal Reprogramming is what happens when that ceiling is breached.
Why it matters
Plans rarely survive contact with real work unchanged, so the ability to re-plan internally lets a project stay aimed at its original targets even as the detailed path to get there shifts. Without it, every minor adjustment would require an unnecessary formal change action.