forProject Encyclopedia

forProject's unified glossary of earned value, scheduling, and government-compliance terms — quick definitions, formulas, and how everything connects.

(click on a term to see details)

A
Above Target Budget (ATB)
The Above Target Budget (ATB) is the amount by which the Total Allocated Budget (TAB) exceeds the Contract Budget Base (CBB).
Government Standards
Accrual
An Accrual is the recording of actual costs for work that has been performed but not yet posted or paid in the accounting system. Sometimes called "Estimated Actual Costs."
EVM Terms
Activity
Activity is another name for a Task, the basic building block of a project schedule.
Scheduling Terms
Actual Cost
Actual Cost is another name for Actual Cost of Work Performed (ACWP) — the cost incurred and recorded in accomplishing the work performed within a given time period, including all recorded incurred costs plus estimated actuals.
EVM Terms
Actual Cost of Work Performed (ACWP)
Actual Cost of Work Performed (ACWP) is the cost incurred and recorded in accomplishing the work performed within a given time period, including all recorded incurred costs plus estimated actuals.
EVM Terms
Apportioned Effort (AE)
Apportioned Effort is an earned value method or technique that is applied in cases where accomplishment is measured in relation to a related, directly measurable task.
EVM Terms
Authorized Unpriced Work (AUW)
Authorized Unpriced Work (AUW) is new work scope the customer has formally authorized and has been estimated, but hasn't yet negotiated a final, definitized price for.
EVM Terms
B
Backward Pass
The Backward Pass is the Critical Path Method calculation that works backward from the project end date to find the latest each task can start and finish without delaying the project.
Scheduling Terms
Baseline
In Earned Value Management (EVM), the Baseline is the approved plan for a project's cost, schedule, and technical scope. Performance is measured against it throughout the project.
EVM Terms
Baseline Change Control
Baseline Change Control is the formal process for reviewing, approving, recording, and communicating changes to the Baseline.
EVM Terms
Baseline Change Request (BCR)
A Baseline Change Request (BCR) is the formal document that proposes a change to the Baseline. It explains why the change is needed and how it affects scope, cost, and schedule.
EVM Terms
Baseline Execution Index (BEI)
The Baseline Execution Index (BEI) is the ratio of tasks actually completed to tasks the baseline schedule says should have been completed by now. It measures how well the project is keeping pace with its plan.
Scheduling Terms
Baseline Schedule
The Baseline Schedule is the approved version of a project schedule. Schedule progress is measured against it.
Scheduling Terms
Basis of Estimate (BOE)
A Basis of Estimate (BOE) is the documented reasoning behind a cost or resource estimate for a specific piece of project scope.
EVM Terms
Bill of Material (BOM)
A Bill of Material (BOM) is a list of the material items, and their quantities, needed to build a product or assembly.
EVM Terms
Budget
In Earned Value Management (EVM), a Budget is the approved resource estimate for a defined scope of work. At any level, the Budget at Completion (BAC) is the sum total of the time-phased Budgeted Cost for Work Scheduled (BCWS) for that work.
EVM Terms
Budget at Completion (BAC)
Budget at Completion (BAC) is the total budget of an element of the project, e.g., a Work Breakdown Structure (WBS) Element, Control Account, or Work Package.
EVM Terms
Budget Log
The Budget Log is a log that tracks changes to the Contract Budget Base (CBB) and other important values over the life of the project.
EVM Terms
Budgeted Cost for Work Performed (BCWP)
Budgeted Cost for Work Performed (BCWP), also called Earned Value, is the budgeted value of the work performed. It can be measured for a single period or cumulative to date.
EVM Terms
Budgeted Cost for Work Scheduled (BCWS)
Budgeted Cost for Work Scheduled (BCWS), also called Planned Value, is the budget for a project element, spread over time according to when the work is scheduled to be done.
EVM Terms
Budgeted Cost of Work Remaining (BCWR)
Budgeted Cost of Work Remaining (BCWR) is the budget for the work not yet performed: Budget at Completion minus cumulative Budgeted Cost for Work Performed (BCWR = BAC − BCWP cum).
EVM Terms
C
Charge Number
Charge Number is a general term for the identifying code that serves as the collection point for costs on a specific piece of work.
EVM Terms
Cognizant Federal Agency (CFA)
The Cognizant Federal Agency (CFA) is the government agency that, on behalf of all federal agencies, sets a contractor's indirect cost rates and administers the Cost Accounting Standards for its contracts.
Government Standards
Constraint
In scheduling, a Constraint is a date limit placed on a task or milestone, such as "start no earlier than" or "finish no later than" a given date.
Scheduling Terms
Contract Budget Base (CBB)
The Contract Budget Base (CBB) is the total budget authorized under a contract: the Negotiated Contract Cost plus the estimated cost of any Authorized Unpriced Work.
EVM Terms
Contract Data Requirements List (CDRL)
A Contract Data Requirements List (CDRL) is the part of a contract that specifies exactly what data items a contractor must deliver, and when.
Government Standards
Contract Funds Status Report (CFSR)
The Contract Funds Status Report (CFSR) is a Department of Defense (DoD) report used to track and forecast the funding needed to complete a contract.
Government Standards
Contract Line Item Number (CLIN)
A Contract Line Item Number (CLIN) is a unique number assigned to a specific item or service in a contract. It's used to manage, account for, bill, and track each deliverable.
Government Standards
Contract Milestone
A Contract Milestone is a type of Milestone that marks an event with contractual significance, such as a commitment in the contract to finish certain work by a certain date.
Scheduling Terms
Contract Performance Report (CPR)
The Contract Performance Report (CPR) was a set of up to five standard report formats showing a contract's cost and schedule performance in Earned Value terms. The CPR was superseded by the Integrated Program Management Report (IPMR), which was in turn superseded by the Integrated Program Management Data and Analysis Report (IPMDAR).
Government Standards
Contract Target Cost (CTC)
Contract Target Cost (CTC) is another name for Negotiated Contract Cost (NCC): the negotiated cost of the original contract plus all negotiated contract changes.
EVM Terms
Contract Target Price (CTP)
Contract Target Price (CTP), for Government contracts, is the negotiated contract cost plus the target profit or fee.
EVM Terms
Contract Type
Contract Type refers to the various forms a contract can take for acquiring goods or services, such as Cost Plus Fixed Fee, Cost Plus Incentive Fee, Firm Fixed Price, Fixed Price Incentive Fee, or Unit Price.
EVM Terms
Contract Work Breakdown Structure (CWBS)
The Contract Work Breakdown Structure (CWBS) is the product-oriented breakdown of a specific Government contract's work, developed in line with MIL-HDBK-881 and the contract's Statement of Work.
Government Standards
Control Account (CA)
A Control Account (CA) is the key management point where scope, schedule, cost, and risk are managed together, and where Earned Value data is typically collected.
EVM Terms
Control Account Manager (CAM)
The Control Account Manager (CAM) is the individual directly responsible for managing a Control Account, including its scope, schedule, cost, and technical performance.
EVM Terms
Control Account Plan (CAP)
A Control Account Plan (CAP) is a document or electronic plan that compiles a Control Account's scope, schedule, and budget information into a single, integrated plan of performance.
EVM Terms
Cost Performance Index (CPI)
The Cost Performance Index (CPI) is a measure of cost efficiency: the ratio of Earned Value, or Budgeted Cost for Work Performed (BCWP), to Actual Cost of Work Performed (ACWP).
EVM Terms
Cost Variance (CV)
Cost Variance (CV) is the difference between Earned Value, or Budgeted Cost for Work Performed (BCWP), and Actual Cost of Work Performed (ACWP). It is a measure of cost performance.
EVM Terms
Cost/Schedule Status Report (C/SSR)
The Cost/Schedule Status Report (C/SSR) is an obsolete, simplified Earned Value Management (EVM) report format once used to provide basic cost and schedule status on smaller government contracts.
Government Standards
Critical Path
The Critical Path is the sequence of linked tasks that determines the project's finish date. Delay any task on it and the project finishes later.
Scheduling Terms
Critical Path Analysis
Critical Path Analysis is another name for the Critical Path Method (CPM), the scheduling calculation that uses task Durations and logical relationships to work out each task's dates and Float and to find the Critical Path.
Scheduling Terms
Critical Path Length Index (CPLI)
The Critical Path Length Index (CPLI) measures how realistic the project's completion date is, based on the remaining length of the critical path and the total float available to the completion task.
Scheduling Terms
Critical Path Method (CPM)
Critical Path Method (CPM) is the scheduling calculation that turns task durations and their logical relationships into dates — determining when each task can start and finish, how much float each one has, and which sequence of tasks sets the project's finish date.
Scheduling Terms
D
DCMA 14-Point Assessment
The DCMA 14-Point Assessment is a set of 14 standard checks, developed by the Defense Contract Management Agency, for judging the health and quality of a project's Integrated Master Schedule.
Scheduling Terms
DCMA EVMS Compliance Metrics (DECM)
The DCMA EVMS Compliance Metrics (DECM) are the Defense Contract Management Agency's standard set of tests for checking whether a contractor's Earned Value Management System is working as the EIA-748 guidelines require.
Government Standards
Defense Contract Audit Agency (DCAA)
The Defense Contract Audit Agency (DCAA) is the U.S. Department of Defense agency responsible for performing contract audits and providing financial advisory services related to DoD contracts.
Government Standards
Defense Contract Management Agency (DCMA)
The Defense Contract Management Agency (DCMA) is the Department of Defense component that works directly with contractors to ensure supplies and services are delivered on time, within cost, and to required performance standards.
Government Standards
Direct Costs
Direct Costs are costs that can be specifically identified with a particular contract or project and are charged to it directly — for example materials, labor, subcontractor charges, or other direct costs such as travel.
EVM Terms
Discrete Effort
Discrete Effort is a classification that identifies work that will earn value based on objective or measurable outputs or work products.
EVM Terms
Discrete Milestone Method
The Discrete Milestone Method is a way of applying the Weighted Milestone Method in which each milestone is all or nothing — its full weight is earned when it's complete, and nothing is earned before.
EVM Terms
Distributed Budget
Distributed Budget is the sum of the budgets, direct and indirect, that have been allocated to Control Accounts and Summary Level Planning Packages through the Control Account planning and Work Authorization process.
EVM Terms
Driving Path
The Driving Path is the sequence of linked tasks that determines the completion date of a specific milestone or task, calculated the same way as the Critical Path but traced back from that milestone rather than from the project finish.
Scheduling Terms
Duration
Duration is the number of work periods — usually working days — that a task spans on its Working Calendar, not counting non-working periods such as weekends and holidays. Duration is not effort: a one-day task might involve one labor hour or a hundred.
Scheduling Terms
Duration Percent Complete
Duration Percent Complete is the percentage of a task's planned Duration that has passed as of the Status Date, calculated as Working Periods (e.g., Days) up through the Status Date divided by total Working Periods in the Duration.
Scheduling Terms
E
Early Finish Date (EF)
The Early Finish Date is the earliest a task can finish: its Early Start Date advanced by the task's Duration across its Working Calendar.
Scheduling Terms
Early Start Date (ES)
The Early Start Date is the earliest a task can begin, given its predecessor relationships — including their type and any Lead or Lag — and its Working Calendar.
Scheduling Terms
Earned Standards Complete Method
Earned Standards Complete is an earned value method or technique that earns value based on pre-established labor-hour standards for each unit of work completed.
EVM Terms
Earned Value (EV)
Earned Value (EV) is another name for Budgeted Cost for Work Performed (BCWP) — the value of work actually performed, expressed in terms of its original budget.
EVM Terms
Earned Value Management (EVM)
Earned Value Management (EVM) is a management approach that integrates a project's scope, schedule, and cost to give objective, data-driven performance measurement and more realistic forecasting.
EVM Terms
Earned Value Management System (EVMS)
An Earned Value Management System (EVMS) is the combination of processes, people, and information and tools that enables an organization to practice effective Earned Value Management.
EVM Terms
Earned Value Method
An Earned Value Method (EV Method) is the specific technique chosen in advance to control how earned value, or Budgeted Cost for Work Performed (BCWP), is calculated as work progresses.
EVM Terms
Elements of Cost (EOC)
Elements of Cost (EOC) are the major categories — such as labor, material, subcontract, and overhead — into which a project's direct and indirect costs are planned and recorded.
EVM Terms
Equivalent Units Method
The Equivalent Units Method is a less common name for the Units Complete Method.
EVM Terms
Estimate at Completion (EAC)
Estimate at Completion (EAC) is the projected total cost of all authorized work, equal to actual costs incurred to date plus the estimated cost to complete the remaining work.
EVM Terms
Estimate to Complete (ETC)
Estimate to Complete (ETC) is the projected cost of finishing all remaining authorized work from this point forward.
EVM Terms
Estimated Actual Costs
Estimated Actual Costs are reasonable estimates of costs already incurred for work performed that haven't yet been posted or paid in the formal accounting system.
EVM Terms
EV Milestone
An EV Milestone is a subdivision of a Work Package, defined so that earned value can be measured at a finer level than the Work Package as a whole.
EVM Terms
EVMS Guidelines
The EVMS Guidelines are the 27 standard requirements, established under ANSI/EIA-748-E, that define what a compliant Earned Value Management System must do.
Government Standards
EVMS Interpretation Guide (EVMSIG)
The EVMS Interpretation Guide (EVMSIG) is the Department of Defense's authoritative interpretation of the EIA-748 guidelines, and the basis on which DoD assesses whether a contractor's Earned Value Management System complies.
Government Standards
F
Float
Float (also called Slack) is the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Forecast Schedule
The Forecast Schedule is the working set of schedule values for every task — actual start, actual finish, and progress for work already performed, plus forecast dates and durations for work still remaining — updated each status cycle.
Scheduling Terms
Formal Reprogramming
Formal Reprogramming is a replan of the remaining work that results in an Over Target Baseline (OTB), an Over Target Schedule (OTS), or both.
Government Standards
Forward Pass
The Forward Pass is the Critical Path Method calculation that works forward from the project start date (or the status date, once work is underway) to find the earliest each task can start and finish.
Scheduling Terms
Forward Pricing Rates Agreement (FPRA)
A Forward Pricing Rates Agreement (FPRA) is a formal bilateral agreement in which the government agrees to accept a contractor's negotiated rates for use in pricing and negotiating future proposals.
Government Standards
Free Float
Free Float (also called Free Slack) is the amount of time a task can be delayed without delaying the early start of its immediately following (successor) tasks.
Scheduling Terms
I
Independent Estimate at Completion (IEAC)
An Independent Estimate at Completion (IEAC) is a cost forecast calculated using a standard formula based on past performance, used to sanity-check the manager's own Estimate at Completion (EAC).
EVM Terms
Indirect Costs
Indirect Costs are costs incurred for common or shared business objectives that can't be traced to a single specific contract or project. Examples of Indirect Costs include Labor Overhead, Material Burden, General & Administrative (G&A), and Cost of Money.
EVM Terms
Integrated Baseline Review (IBR)
An Integrated Baseline Review (IBR) is a joint government/contractor review held to confirm that a project's Performance Measurement Baseline (PMB) is realistic and complete.
Government Standards
Integrated Master Plan (IMP)
The Integrated Master Plan (IMP) is an event-based project plan: a hierarchy of events, each supported by accomplishments, with each accomplishment tied to criteria that show it's complete.
EVM Terms
Integrated Master Schedule (IMS)
The Integrated Master Schedule (IMS) is a detailed, networked schedule containing all the Work Packages, Planning Packages, and lower-level tasks needed to support a project's events, accomplishments, and criteria.
Scheduling Terms
Integrated Product Team (IPT)
An Integrated Product Team (IPT) is a multidisciplinary team given management responsibility for one or more elements of a project.
EVM Terms
Integrated Program Management Data and Analysis Report (IPMDAR)
The Integrated Program Management Data and Analysis Report (IPMDAR) is a U.S. government contract report that shows current and forecast contract cost and schedule performance. It's issued under Data Item Description (DID) DI-MGMT-81861 available at: https://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=278901
Government Standards
Integrated Program Management Report (IPMR)
The Integrated Program Management Report (IPMR) is a set of standardized reports required on many U.S. government contracts with a formal Earned Value Management requirement. Note: The IPMR has effectively been superseded by the Integrated Program Management Data and Analysis Report (IPMDAR).
Government Standards
Internal Re-planning
Internal Re-planning is any change to a project's budgets that stays within the existing contract scope and keeps the Total Allocated Budget (TAB) under the Contract Budget Base (CBB).
EVM Terms
IPT Leader
An Integrated Product Team (IPT) Leader is the individual identified as responsible for that team.
EVM Terms
L
Lag
A Lag is a delay built into a logical relationship, holding the successor task back for a set amount of time after the predecessor condition is met.
Scheduling Terms
Late Finish Date (LF)
The Late Finish Date is the latest a task can finish without delaying the project, given its successor relationships — including their type and any Lead or Lag — and its Working Calendar.
Scheduling Terms
Late Start Date (LS)
The Late Start Date is the latest a task can start without delaying the project: its Late Finish Date less the task's Duration across its Working Calendar.
Scheduling Terms
Latest Revised Estimate (LRE)
Latest Revised Estimate (LRE) is another name for the Estimate at Completion (EAC): the current forecast of what the work will cost when it's finished.
EVM Terms
Lead
A Lead is a planned overlap built into a logical relationship, allowing the successor task to start before the predecessor condition is fully met.
Scheduling Terms
Level of Effort (LOE)
Level of Effort (LOE) is work of a general or supportive nature — such as supervision or contract administration — that doesn't produce a definite end product.
EVM Terms
O
Organizational Breakdown Structure (OBS)
The Organizational Breakdown Structure (OBS) is the organizational structure — including major subcontractors — responsible for accomplishing a project's authorized work.
EVM Terms
Other Direct Cost (ODC)
Other Direct Costs (ODC) are costs charged directly to a project that don't fall under the main direct cost categories of labor or material.
EVM Terms
Over Target Baseline (OTB)
An Over Target Baseline (OTB) is a revised Performance Measurement Baseline, set through Formal Reprogramming, in which the Total Allocated Budget (TAB) exceeds the Contract Budget Base (CBB). The amount above the CBB is the Above Target Budget (ATB).
Government Standards
Over Target Schedule (OTS)
An Over Target Schedule (OTS) exists when the Baseline Schedule extends beyond the contractually committed finish date.
Government Standards
Overhead
Overhead is a category of Indirect Cost covering shared costs that support a particular function, facility, or business unit rather than any single project.
EVM Terms
P
Percent Complete
Percent Complete is a general measure of progress on a task or Work Package, expressed in various ways depending on what's being measured.
EVM Terms
Percent Complete (EV Method)
Percent Complete (EV Method) is an earned value method or technique in which a Work Package or task earns value based on an assessment of how much of its work is complete.
EVM Terms
Percent Spent
Percent Spent measures how much has been spent on a task so far compared to its total expected cost.
EVM Terms
Performance Measurement Baseline (PMB)
The Performance Measurement Baseline (PMB) is the time-phased budget plan that Earned Value performance is measured against. It includes all budgets, direct and indirect, allocated to Control Accounts and Summary Level Planning Packages, plus any Undistributed Budget.
EVM Terms
Performing Organization
The Performing Organization is the functional organization or department assigned to perform a defined scope of work, such as a Control Account or Work Package.
EVM Terms
Physical Percent Complete
Physical Percent Complete is the assessed progress of actual work accomplished on a task, independent of the passage of time against its schedule.
EVM Terms
Planned Value (PV)
Planned Value (PV) is another name for Budgeted Cost for Work Scheduled (BCWS): the time-phased budget for the work scheduled to be performed.
EVM Terms
Planning & Scheduling Excellence Guide (PASEG)
The Planning & Scheduling Excellence Guide (PASEG) is the National Defense Industrial Association (NDIA) Integrated Program Management Division's reference guide on building, using, and maintaining an Integrated Master Schedule.
Government Standards
Planning Package
A Planning Package is a future portion of work within a Control Account that hasn't yet been broken down into detailed Work Packages.
EVM Terms
Program Manager (PM)
The Program Manager (PM) is the individual with overall responsibility for the cost, schedule, and technical performance of a program or project, including making the tradeoffs necessary to meet these objectives.
EVM Terms
R
Rebaselining
Rebaselining is the general term for revising the remaining baseline plan. Whether a rebaseline counts as Internal Re-planning or Formal Reprogramming depends on the result: if the Total Allocated Budget stays within the Contract Budget Base and the schedule stays within the contract dates, it's Internal Re-planning; if the TAB exceeds the CBB, or the baseline schedule extends beyond the contract dates, it's Formal Reprogramming.
EVM Terms
Relationship
A Relationship is the logical link between two schedule tasks that establishes the order in which they must occur, such as Finish-to-Start, Start-to-Start, Finish-to-Finish, or Start-to-Finish.
Scheduling Terms
Reprogramming Adjustment
Reprogramming Adjustments are the changes a contractor reports to the customer when it formally reprograms: the reset of cost and schedule variances on completed work, and the budget added above the Contract Budget Base.
Government Standards
Resource
A Resource is any personnel, material, equipment, service, or other cost needed to complete project work.
Scheduling Terms
Responsibility Assignment Matrix (RAM)
The Responsibility Assignment Matrix (RAM) is a chart showing how Work Breakdown Structure (WBS) elements map to the organizations responsible for completing them.
EVM Terms
Responsible Organization
The Responsible Organization is the organization or Integrated Product Team (IPT) assigned full responsibility for the scope, schedule, and cost performance of a Control Account or Summary Level Planning Package (SLPP).
EVM Terms
S
Schedule
A Schedule is a plan that shows when specified work will be performed to meet project objectives on time.
Scheduling Terms
Schedule Performance Index (SPI)
The Schedule Performance Index (SPI) is a measure of schedule efficiency: the ratio of Earned Value, or Budgeted Cost for Work Performed (BCWP), to Planned Value, or Budgeted Cost for Work Scheduled (BCWS). It measures how much work has been accomplished in comparison with the baseline plan.
EVM Terms
Schedule Risk Assessment (SRA)
A Schedule Risk Assessment (SRA) is a process that uses statistical or probabilistic techniques to identify and quantify technical, programmatic, and schedule risks affecting a project's schedule.
Scheduling Terms
Schedule Variance (SV)
Schedule Variance (SV) is the difference between Earned Value, or Budgeted Cost for Work Performed (BCWP), and Planned Value, or Budgeted Cost for Work Scheduled (BCWS).
EVM Terms
Schedule Visibility Task (SVT)
A Schedule Visibility Task (SVT) is a task with no resources, shown in the schedule for visibility only, that represents work or waiting that affects the project but isn't part of its Performance Measurement Baseline (PMB).
Scheduling Terms
Simulation
Simulation is a technique that uses random numbers and probability — most commonly Monte Carlo simulation — to test how uncertainty affects a schedule's reliability.
Scheduling Terms
Single Point Adjustment (SPA)
A Single Point Adjustment (SPA) resets cumulative Schedule Variance, Cost Variance, or both to zero, using one-time adjustments to BCWS and/or BCWP in the current period, to give variance reporting a fresh start before the remaining work is replanned.
Government Standards
Slack
Slack is another name for Float — the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Soft Constraint
A Soft Constraint is a Constraint that guides when a task or milestone is scheduled, such as how early it can start or finish, without inhibiting the logical flow of the schedule.
Scheduling Terms
Start/Finish Method
The Start/Finish Method is an earned value method or technique where a set percentage of a Work Package's or task's value is earned when it starts, and the remainder is earned when it finishes.
EVM Terms
Statement of Work (SOW)
A Statement of Work (SOW) is the document that defines the work scope of a project or a specific element such as a Work Breakdown Structure (WBS) element, Control Account, or Work Package.
EVM Terms
Summary Level Planning Package (SLPP)
A Summary Level Planning Package (SLPP) represents defined far-term work that isn't yet practical to plan in Control Accounts.
EVM Terms
T
Task
A Task, also called an Activity, is a distinct piece of work with a clear start and finish, and the basic building block of a project schedule.
Scheduling Terms
To Complete Performance Index – BAC (TCPI)
To Complete Performance Index - BAC, or TCPI (BAC), shows whether the original Budget at Completion (BAC) is still achievable. It's the cost efficiency needed on the remaining work to finish within that budget.
EVM Terms
To Complete Performance Index – EAC (TCPI)
To Complete Performance Index - EAC, or TCPI (EAC), calculates the cost efficiency that must be achieved on the remaining work to finish at the current Estimate at Completion.
EVM Terms
Total Allocated Budget (TAB)
The Total Allocated Budget (TAB) is the sum of all budget allocated to a contract, made up of the Performance Measurement Baseline (PMB) plus Management Reserve (MR).
EVM Terms
Total Float
Total Float (also called Total Slack) is the amount of time a task can be delayed from its Early Start without delaying the project finish date or any other date the schedule is required to meet.
Scheduling Terms
V
Variance Analysis Report (VAR)
A Variance Analysis Report (VAR) identifies significant Cost and Schedule Variances, including Variance at Completion (VAC), on a project, along with their size, causes, immediate impact, and planned corrective actions.
Government Standards
Variance Analysis Thresholds
Variance Analysis Thresholds are the amount and percentage criteria that determine when a Cost or Schedule Variance is significant enough to require formal written analysis rather than routine tracking.
EVM Terms
Variance at Completion (VAC)
Variance at Completion (VAC) is the difference between the Budget at Completion (BAC) and the current approved Estimate at Completion (EAC). It shows whether the work is expected to finish over or under budget.
EVM Terms
Vertical Schedule Integration
Vertical Schedule Integration is the practice of tying higher-level summary schedules to lower-level, detailed schedules so that data is consistent across all levels of the project's schedule hierarchy.
Scheduling Terms
W
WBS Dictionary
The Work Breakdown Structure (WBS) Dictionary is a document that gives a brief narrative definition of each element of the Work Breakdown Structure, describing its work scope and deliverables.
EVM Terms
Weighted Milestone Method
The Weighted Milestone Method is an earned value method or technique that breaks a Work Package into several milestones, each assigned a weight — a share of the Work Package's budget — earned as that milestone is achieved.
EVM Terms
Work Authorization (WA)
Work Authorization is the process of reaching agreement between the Project Manager and the manager of the performing organization on a defined element of work, together with its schedule, budget, and Statement of Work. The agreement is recorded in a Work Authorization Document (WAD).
EVM Terms
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) is a product-oriented, hierarchical breakdown of all the work to be performed on a project, organizing hardware, software, services, and other deliverables into a single unifying structure.
EVM Terms
Work Package (WP)
A Work Package (WP) is a natural subdivision of the tasks within a Control Account, and the point at which work is planned, progress is measured, and earned value is computed.
EVM Terms
Working Calendar
A Working Calendar sets which periods are available for work, such as the working hours in a day, the working days in a week, and holidays or other non-working days.
Scheduling Terms