Total Allocated Budget (TAB)
Unless an Over Target Baseline (OTB) has been established, TAB is exactly equal to the Contract Budget Base (CBB). In an OTB, TAB = CBB + Above Target Budget (ATB). TAB represents the full budget a contractor has been given to accomplish authorized work, split between the baseline used to measure performance and reserve held back for unforeseen risk.
What this means for you
The Total Allocated Budget (TAB) is the sum of all Control Account and Summary Level Planning Package (SLPP) budgets, any balance in Undistributed Budget (UB), and the Management Reserve (MR). Comparing it with the Contract Budget Base (CBB) confirms that the budget allocated in the project plan doesn't exceed the Negotiated Contract Cost (NCC) plus any Authorized, Unpriced Work (AUW). In short, it makes sure the allocated budget doesn't exceed the total authorized budget on the project.