Lag
Lag is a delay applied to a logical relationship to impose a "gap" between two tasks. It's entered as a positive amount of time on the relationship itself, not as a task, so it carries no resources and can't be statused. When the wait needs tracking or could affect the Critical Path, a Schedule Visibility Task is usually a better choice. Overuse of Lag can mean the schedule isn't modeling hand-offs in enough detail.
What this means for you
A Lag is quick to add, which is exactly why it gets overused. Time sitting in a Lag can't be statused, doesn't carry resources, and can quietly sit on the Critical Path where nobody is watching it. Every Lag should represent a real, explainable wait rather than a convenient way to push a date.