Lag

Scheduling Terms Reviewed by forProject Technology - updated Sep 2026
Quick definition: A Lag is a delay built into a logical relationship, holding the successor task back for a set amount of time after the predecessor condition is met.

Lag models real waiting time between two tasks — the classic example is waiting for paint to dry before the next step can begin. It is entered as a positive amount of time on the relationship itself, not as a task, so no resources are charged and no progress is reported while the Lag runs. Because a Lag is invisible in that way, it's worth considering a Schedule Visibility Task instead whenever the wait needs to be statused, is likely to differ from the planned delay, could land on the Critical Path or a Driving Path, or matters for traceability to other schedules. Unnecessary use of Lag can indicate a schedule that isn't modeling hand-offs at sufficient detail.

Why it matters

A Lag is quick to add, which is exactly why it gets overused. Time sitting in a Lag can't be statused, doesn't carry resources, and can quietly sit on the Critical Path where nobody is watching it. Every Lag should represent a real, explainable wait rather than a convenient way to push a date.

Also known as
N/A
Used in
Schedule network modeling; Critical Path Method calculations; schedule health assessment

See also

FAQ

How is a Lag different from just adding a task?
A Lag is an attribute of the relationship between two tasks, so it has no duration of its own to status and no resources assigned. A Schedule Visibility Task models the same wait as a real task, which can be statused and tracked — generally preferable where the wait matters.
Can a Lag be entered as a percentage?
Some tools allow it, but it's best avoided: a percentage-based value moves with the predecessor's duration, so it can drift as the schedule changes.
Definition maintained by forProject Technology.