Early Start Date (ES)
Calculated during the Forward Pass, the Early Start Date is the soonest a task could begin once every predecessor relationship is satisfied. What that requires depends on the relationship type: a Finish-to-Start predecessor must finish first, while a Start-to-Start predecessor need only start. Any lead or lag shifts the result further, and the task's working calendar determines the actual date, since non-working days are skipped. It works alongside the Early Finish Date to establish the earliest possible schedule for each task.
Why it matters
The Early Start Date, compared against the Late Start Date, shows how much flexibility a task has before it must begin — a key input for calculating float and identifying the Critical Path. It's foundational to how scheduling software calculates the overall schedule.