Late Finish Date (LF)
Calculated during the Backward Pass, working back from the project finish. Each successor relationship imposes a limit on when the task must finish, and the earliest of those limits governs. As on the Forward Pass, the relationship type matters — a Finish-to-Start successor constrains the task's finish, while a Finish-to-Finish successor constrains it differently — and leads, lags, and the working calendar all shift the result. Tasks with little or no gap between their Early Finish Date and Late Finish Date have little float and sit close to, or on, the Critical Path.
Why it matters
The Late Finish Date defines exactly how much scheduling flexibility a task has before it starts threatening the project's finish date. It's one half of the float calculation that tells a scheduler where the real risk sits.