Forward Pass
The Forward Pass starts at the project start date and moves through the schedule one task at a time, following the dependencies that link each task to the next. A task's Early Start Date is set by the finish of the tasks that must come before it, and its Early Finish Date is that Early Start Date plus the task's duration. Where several tasks must finish first, the latest of them governs. The final Early Finish Date is the earliest the project can complete if everything goes to plan. Lags, leads, task Working Calendars, and constraints all affect the result, which is why a Forward Pass is only as trustworthy as the schedule logic behind it.
Why it matters
The Forward Pass produces every early date in the schedule, which is the basis for judging whether the plan can meet its required dates at all. Because the calculation is performed by the scheduling software, the scheduler's real job is making sure the durations, logic, Working Calendars, and constraints feeding it are sound — bad inputs produce precise, confident, and wrong dates.
See also
FAQ
© 2026 forProject Technology, Inc.
