Percent Complete (EV Method)
Also called the Manager's Assessment method, Percent Complete is the most widely used earning technique in practice. Rather than tying credit to fixed milestones or unit counts, it asks the responsible manager to assess how far the work has progressed. That flexibility is why it is applied so broadly — and its reliance on judgment is its weakness. The accepted best practice is therefore to require Quantifiable Backup Data wherever Percent Complete is used, so the figure claimed rests on documented evidence rather than opinion.
Why it matters
Because it can be applied to almost any kind of work, Percent Complete carries a large share of the earned value reported on most projects. That makes the quality of the underlying assessment a major factor in whether performance data can be trusted at all. Requiring Quantifiable Backup Data is what turns a judgment into something a reviewer can check.