Before work begins, each Work Package is assigned an EV Method that defines how its earned value will be calculated. Common choices include Percent Complete, Weighted Milestone, Units Complete (also called Equivalent Units), Level of Effort (LOE), and Apportioned Effort. The optimal choice depends on the nature of the work: whether its output can be measured objectively, whether progress is tied only to the passage of time, or whether it moves in step with other measured work.
What this means for you
Choosing an appropriate EV Method matters because a poor fit can distort performance data — for example, using Level of Effort for discrete work can mask real schedule problems since LOE always earns value exactly as planned. Locking in the method before work starts also keeps earned value reporting objective, rather than left to subjective mid-project judgment calls.