Discrete Milestone Method
Under the Weighted Milestone Method, a Work Package is broken into milestones that each carry a share of the budget. Discrete Milestone is one of two ways to take credit at those milestones: no partial progress is recognized, so a milestone earns its full weight the moment it's achieved and nothing until then. The alternative is Measured Milestone, which allows partial progress within a milestone. Discrete is the stricter of the two and suits milestones with a clear, verifiable completion point.
Why it matters
Because credit is only taken on completion of a defined milestone, this method reduces the subjectivity involved in claiming progress compared to methods based on estimated percent complete. That makes it a popular choice for work with clear, verifiable completion points.