Work Package (WP)
A Work Package represents a definable unit of work performed at whatever level is normal for program management. It might be a design job, a build-to-package, a shop order, or another task assignable to a single organizational element. Each one has clear start and completion dates and, where applicable, interim milestones marking physical progress. A single Earned Value Method is assigned to each Work Package, which determines how its Budgeted Cost for Work Performed (BCWP) is calculated — so how a Work Package is defined and scoped directly governs how its progress can be measured.
What this means for you
The Work Package is where earned value actually gets measured day to day, making it the foundation that all higher-level cost and schedule performance rolls up from. If Work Packages aren't well defined and distinct from one another, the earned value numbers built on top of them won't be reliable either.