Apportioned Effort (AE)
Apportioned Effort applies when a task's own output isn't practical to measure discretely, so its earned value is instead tied to the progress of another, related task that is measured directly. As that base task earns value, the apportioned task earns value automatically. The base must itself be Discrete Effort — Apportioned Effort cannot be tied to Level of Effort, because that would make it earn by the passage of time rather than by accomplishment.
What this means for you
Apportioned Effort allows value to be earned in direct proportion to the supported task, eliminating the need for additional progress reporting. Apportioned is often preferable to Level of Effort measurement, where value is earned as planned solely based on the passage of time.