Estimate to Complete (ETC)
ETC is the forecast of the expected cost to complete the remaining work. It's the responsible manager's estimate, usually prepared by the Control Account Manager (CAM), of what the remaining work will cost. Good practice is to consider past cost performance as one factor, along with remaining scope and known risks, but the estimate is still a judgment. ETC is one of the two building blocks of the Estimate at Completion (EAC).
What this means for you
A realistic ETC is critical because it feeds directly into the Estimate at Completion (EAC). An overly optimistic ETC can hide a potential cost overrun until it's too late to correct. Reviewing and updating ETC regularly keeps the overall cost forecast credible.