Estimate at Completion (EAC)
EAC is calculated as EAC = ACWP(cumulative) + ETC — what's already been spent, plus a fresh estimate of what it will take to finish. It's typically built up from Work Package-level estimates and rolled up to the total project. Unlike the original Budget at Completion (BAC), EAC reflects actual performance and current judgment, so it can move up or down as the project progresses.
Why it matters
EAC is the number management and customers watch most closely, because it answers the practical question of what the project will actually cost when it's done. Comparing EAC to BAC (via Variance at Completion) shows whether the project is trending toward a cost overrun or underrun well before completion.