Estimate at Completion (EAC)
The Estimate at Completion (EAC) is the current forecast of what the work will cost when it's finished. It's simple addition: the costs already incurred plus the latest estimate of the cost to finish the remaining work, or EAC = cumulative Actual Cost of Work Performed (ACWP) + Estimate to Complete (ETC). Past performance affects the EAC only indirectly, through the actual costs already recorded and through the judgment of the person preparing the ETC. Unlike the Budget at Completion (BAC), EAC changes whenever actual costs are recorded or the ETC is updated. It's typically built up from Work Package estimates and rolled up to higher levels.
What this means for you
EAC is the number management and customers watch most closely, because it answers the practical question of what the project will actually cost when it's done. Comparing EAC to BAC (via Variance at Completion) shows whether the project is trending toward a cost overrun or underrun well before completion.