forProject Encyclopedia

forProject's unified glossary of earned value, scheduling, and government-compliance terms — quick definitions, formulas, and how everything connects.

(click on a term to see details)

A
Accrual
An Accrual is the recording of actual costs for work that has been performed but not yet posted or paid in the accounting system. Sometimes called "Estimated Actual Costs."
EVM Terms
Actual Cost
Actual Cost is another name for Actual Cost of Work Performed (ACWP) — the cost incurred and recorded in accomplishing the work performed within a given time period, including all recorded incurred costs plus estimated actuals.
EVM Terms
Actual Cost of Work Performed (ACWP)
Actual Cost of Work Performed (ACWP) is the cost incurred and recorded in accomplishing the work performed within a given time period, including all recorded incurred costs plus estimated actuals.
EVM Terms
Apportioned Effort (AE)
Apportioned Effort is an earned value method or technique that is applied in cases where accomplishment is measured in relation to a related, directly measurable task.
EVM Terms
Authorized Unpriced Work (AUW)
Authorized Unpriced Work (AUW) is new work scope the customer has formally authorized and has been estimated, but hasn't yet negotiated a final, definitized price for.
EVM Terms
B
Baseline
In Earned Value Management (EVM), the Baseline is the approved plan for a project's cost, schedule, and technical scope. Performance is measured against it throughout the project.
EVM Terms
Baseline Change Control
Baseline Change Control is the formal process for reviewing, approving, recording, and communicating changes to the Baseline.
EVM Terms
Baseline Change Request (BCR)
A Baseline Change Request (BCR) is the formal document that proposes a change to the Baseline. It explains why the change is needed and how it affects scope, cost, and schedule.
EVM Terms
Basis of Estimate (BOE)
A Basis of Estimate (BOE) is the documented reasoning behind a cost or resource estimate for a specific piece of project scope.
EVM Terms
Bill of Material (BOM)
A Bill of Material (BOM) is a list of the material items, and their quantities, needed to build a product or assembly.
EVM Terms
Budget
In Earned Value Management (EVM), a Budget is the approved resource estimate for a defined scope of work. At any level, the Budget at Completion (BAC) is the sum total of the time-phased Budgeted Cost for Work Scheduled (BCWS) for that work.
EVM Terms
Budget at Completion (BAC)
Budget at Completion (BAC) is the total budget of an element of the project, e.g., a Work Breakdown Structure (WBS) Element, Control Account, or Work Package.
EVM Terms
Budget Log
The Budget Log is a log that tracks changes to the Contract Budget Base (CBB) and other important values over the life of the project.
EVM Terms
Budgeted Cost for Work Performed (BCWP)
Budgeted Cost for Work Performed (BCWP), also called Earned Value, is the budgeted value of the work performed. It can be measured for a single period or cumulative to date.
EVM Terms
Budgeted Cost for Work Scheduled (BCWS)
Budgeted Cost for Work Scheduled (BCWS), also called Planned Value, is the budget for a project element, spread over time according to when the work is scheduled to be done.
EVM Terms
Budgeted Cost of Work Remaining (BCWR)
Budgeted Cost of Work Remaining (BCWR) is the budget for the work not yet performed: Budget at Completion minus cumulative Budgeted Cost for Work Performed (BCWR = BAC − BCWP cum).
EVM Terms
C
Charge Number
Charge Number is a general term for the identifying code that serves as the collection point for costs on a specific piece of work.
EVM Terms
Contract Budget Base (CBB)
The Contract Budget Base (CBB) is the total budget authorized under a contract: the Negotiated Contract Cost plus the estimated cost of any Authorized Unpriced Work.
EVM Terms
Contract Target Cost (CTC)
Contract Target Cost (CTC) is another name for Negotiated Contract Cost (NCC): the negotiated cost of the original contract plus all negotiated contract changes.
EVM Terms
Contract Target Price (CTP)
Contract Target Price (CTP), for Government contracts, is the negotiated contract cost plus the target profit or fee.
EVM Terms
Contract Type
Contract Type refers to the various forms a contract can take for acquiring goods or services, such as Cost Plus Fixed Fee, Cost Plus Incentive Fee, Firm Fixed Price, Fixed Price Incentive Fee, or Unit Price.
EVM Terms
Control Account (CA)
A Control Account (CA) is the key management point where scope, schedule, cost, and risk are managed together, and where Earned Value data is typically collected.
EVM Terms
Control Account Manager (CAM)
The Control Account Manager (CAM) is the individual directly responsible for managing a Control Account, including its scope, schedule, cost, and technical performance.
EVM Terms
Control Account Plan (CAP)
A Control Account Plan (CAP) is a document or electronic plan that compiles a Control Account's scope, schedule, and budget information into a single, integrated plan of performance.
EVM Terms
Cost Performance Index (CPI)
The Cost Performance Index (CPI) is a measure of cost efficiency: the ratio of Earned Value, or Budgeted Cost for Work Performed (BCWP), to Actual Cost of Work Performed (ACWP).
EVM Terms
Cost Variance (CV)
Cost Variance (CV) is the difference between Earned Value, or Budgeted Cost for Work Performed (BCWP), and Actual Cost of Work Performed (ACWP). It is a measure of cost performance.
EVM Terms
D
Direct Costs
Direct Costs are costs that can be specifically identified with a particular contract or project and are charged to it directly — for example materials, labor, subcontractor charges, or other direct costs such as travel.
EVM Terms
Discrete Effort
Discrete Effort is a classification that identifies work that will earn value based on objective or measurable outputs or work products.
EVM Terms
Discrete Milestone Method
The Discrete Milestone Method is a way of applying the Weighted Milestone Method in which each milestone is all or nothing — its full weight is earned when it's complete, and nothing is earned before.
EVM Terms
Distributed Budget
Distributed Budget is the sum of the budgets, direct and indirect, that have been allocated to Control Accounts and Summary Level Planning Packages through the Control Account planning and Work Authorization process.
EVM Terms
E
Earned Standards Complete Method
Earned Standards Complete is an earned value method or technique that earns value based on pre-established labor-hour standards for each unit of work completed.
EVM Terms
Earned Value (EV)
Earned Value (EV) is another name for Budgeted Cost for Work Performed (BCWP) — the value of work actually performed, expressed in terms of its original budget.
EVM Terms
Earned Value Management (EVM)
Earned Value Management (EVM) is a management approach that integrates a project's scope, schedule, and cost to give objective, data-driven performance measurement and more realistic forecasting.
EVM Terms
Earned Value Management System (EVMS)
An Earned Value Management System (EVMS) is the combination of processes, people, and information and tools that enables an organization to practice effective Earned Value Management.
EVM Terms
Earned Value Method
An Earned Value Method (EV Method) is the specific technique chosen in advance to control how earned value, or Budgeted Cost for Work Performed (BCWP), is calculated as work progresses.
EVM Terms
Elements of Cost (EOC)
Elements of Cost (EOC) are the major categories — such as labor, material, subcontract, and overhead — into which a project's direct and indirect costs are planned and recorded.
EVM Terms
Equivalent Units Method
The Equivalent Units Method is a less common name for the Units Complete Method.
EVM Terms
Estimate at Completion (EAC)
Estimate at Completion (EAC) is the projected total cost of all authorized work, equal to actual costs incurred to date plus the estimated cost to complete the remaining work.
EVM Terms
Estimate to Complete (ETC)
Estimate to Complete (ETC) is the projected cost of finishing all remaining authorized work from this point forward.
EVM Terms
Estimated Actual Costs
Estimated Actual Costs are reasonable estimates of costs already incurred for work performed that haven't yet been posted or paid in the formal accounting system.
EVM Terms
EV Milestone
An EV Milestone is a subdivision of a Work Package, defined so that earned value can be measured at a finer level than the Work Package as a whole.
EVM Terms
I
Independent Estimate at Completion (IEAC)
An Independent Estimate at Completion (IEAC) is a cost forecast calculated using a standard formula based on past performance, used to sanity-check the manager's own Estimate at Completion (EAC).
EVM Terms
Indirect Costs
Indirect Costs are costs incurred for common or shared business objectives that can't be traced to a single specific contract or project. Examples of Indirect Costs include Labor Overhead, Material Burden, General & Administrative (G&A), and Cost of Money.
EVM Terms
Integrated Master Plan (IMP)
The Integrated Master Plan (IMP) is an event-based project plan: a hierarchy of events, each supported by accomplishments, with each accomplishment tied to criteria that show it's complete.
EVM Terms
Integrated Product Team (IPT)
An Integrated Product Team (IPT) is a multidisciplinary team given management responsibility for one or more elements of a project.
EVM Terms
Internal Re-planning
Internal Re-planning is any change to a project's budgets that stays within the existing contract scope and keeps the Total Allocated Budget (TAB) under the Contract Budget Base (CBB).
EVM Terms
IPT Leader
An Integrated Product Team (IPT) Leader is the individual identified as responsible for that team.
EVM Terms
P
Percent Complete
Percent Complete is a general measure of progress on a task or Work Package, expressed in various ways depending on what's being measured.
EVM Terms
Percent Complete (EV Method)
Percent Complete (EV Method) is an earned value method or technique in which a Work Package or task earns value based on an assessment of how much of its work is complete.
EVM Terms
Percent Spent
Percent Spent measures how much has been spent on a task so far compared to its total expected cost.
EVM Terms
Performance Measurement Baseline (PMB)
The Performance Measurement Baseline (PMB) is the time-phased budget plan that Earned Value performance is measured against. It includes all budgets, direct and indirect, allocated to Control Accounts and Summary Level Planning Packages, plus any Undistributed Budget.
EVM Terms
Performing Organization
The Performing Organization is the functional organization or department assigned to perform a defined scope of work, such as a Control Account or Work Package.
EVM Terms
Physical Percent Complete
Physical Percent Complete is the assessed progress of actual work accomplished on a task, independent of the passage of time against its schedule.
EVM Terms
Planned Value (PV)
Planned Value (PV) is another name for Budgeted Cost for Work Scheduled (BCWS): the time-phased budget for the work scheduled to be performed.
EVM Terms
Planning Package
A Planning Package is a future portion of work within a Control Account that hasn't yet been broken down into detailed Work Packages.
EVM Terms
Program Manager (PM)
The Program Manager (PM) is the individual with overall responsibility for the cost, schedule, and technical performance of a program or project, including making the tradeoffs necessary to meet these objectives.
EVM Terms
R
Rebaselining
Rebaselining is the general term for revising the remaining baseline plan. Whether a rebaseline counts as Internal Re-planning or Formal Reprogramming depends on the result: if the Total Allocated Budget stays within the Contract Budget Base and the schedule stays within the contract dates, it's Internal Re-planning; if the TAB exceeds the CBB, or the baseline schedule extends beyond the contract dates, it's Formal Reprogramming.
EVM Terms
Responsibility Assignment Matrix (RAM)
The Responsibility Assignment Matrix (RAM) is a chart showing how Work Breakdown Structure (WBS) elements map to the organizations responsible for completing them.
EVM Terms
Responsible Organization
The Responsible Organization is the organization or Integrated Product Team (IPT) assigned full responsibility for the scope, schedule, and cost performance of a Control Account or Summary Level Planning Package (SLPP).
EVM Terms
S
Schedule Performance Index (SPI)
The Schedule Performance Index (SPI) is a measure of schedule efficiency: the ratio of Earned Value, or Budgeted Cost for Work Performed (BCWP), to Planned Value, or Budgeted Cost for Work Scheduled (BCWS). It measures how much work has been accomplished in comparison with the baseline plan.
EVM Terms
Schedule Variance (SV)
Schedule Variance (SV) is the difference between Earned Value, or Budgeted Cost for Work Performed (BCWP), and Planned Value, or Budgeted Cost for Work Scheduled (BCWS).
EVM Terms
Start/Finish Method
The Start/Finish Method is an earned value method or technique where a set percentage of a Work Package's or task's value is earned when it starts, and the remainder is earned when it finishes.
EVM Terms
Statement of Work (SOW)
A Statement of Work (SOW) is the document that defines the work scope of a project or a specific element such as a Work Breakdown Structure (WBS) element, Control Account, or Work Package.
EVM Terms
Summary Level Planning Package (SLPP)
A Summary Level Planning Package (SLPP) represents defined far-term work that isn't yet practical to plan in Control Accounts.
EVM Terms
W
WBS Dictionary
The Work Breakdown Structure (WBS) Dictionary is a document that gives a brief narrative definition of each element of the Work Breakdown Structure, describing its work scope and deliverables.
EVM Terms
Weighted Milestone Method
The Weighted Milestone Method is an earned value method or technique that breaks a Work Package into several milestones, each assigned a weight — a share of the Work Package's budget — earned as that milestone is achieved.
EVM Terms
Work Authorization (WA)
Work Authorization is the process of reaching agreement between the Project Manager and the manager of the performing organization on a defined element of work, together with its schedule, budget, and Statement of Work. The agreement is recorded in a Work Authorization Document (WAD).
EVM Terms
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) is a product-oriented, hierarchical breakdown of all the work to be performed on a project, organizing hardware, software, services, and other deliverables into a single unifying structure.
EVM Terms
Work Package (WP)
A Work Package (WP) is a natural subdivision of the tasks within a Control Account, and the point at which work is planned, progress is measured, and earned value is computed.
EVM Terms