Work Authorization (WA)

EVM Terms Reviewed by forProject Technology - updated Sep 2026
Quick definition: Work Authorization is the process of reaching agreement between the Project Manager and the manager of the performing organization on a defined element of work, together with its schedule, budget, and Statement of Work. The agreement is recorded in a Work Authorization Document (WAD).

Work Authorization is bilateral: the performing organization accepts the scope, schedule, and budget rather than simply being handed them, and that acceptance is what makes the commitment meaningful. The WAD records the agreement and serves as its audit trail. Authorization can be issued at the project level or at lower levels, such as Work Breakdown Structure (WBS) Elements, Control Accounts, or Work Packages. It's the formal step that turns planned work into work someone is authorized to perform and charge to.

What this means for you

Work generally shouldn't start or be charged to a project without one — it's the control point that keeps spending tied to approved scope, schedule, and budget. That traceability is central to demonstrating that a project's costs are properly authorized and controlled.

Also known as
Work Authorization Document (WAD)
Used in
Work Package and Control Account setup

FAQ

What is the difference between Work Authorization and a Work Authorization Document?
Work Authorization is the process of reaching agreement on the scope, schedule, and budget for a piece of work. The Work Authorization Document is the record of that agreement.
What levels can a Work Authorization apply to?
It can be issued at the overall project level or lower, such as WBS Elements, Control Accounts, or Work Packages.
Definition maintained by forProject Technology.