Schedule Performance Index (SPI)
SPI is a measure of schedule efficiency. It is the ratio of the value earned (based on accomplishments) over the value of the work scheduled to be accomplished. In EVMS terms, it is the ratio of Budgeted Cost for Work Performed (BCWP) divided by Budgeted Cost for Work Scheduled (BCWS). An SPI above 1.0 indicates favorable schedule efficiency. An SPI below 1.0 indicates unfavorable schedule efficiency. SPI can be calculated for the current period or cumulative to date.
What this means for you
SPI gives a quick, single-number read on schedule health, so managers can spot slippage early. It works alongside the Cost Performance Index (CPI) to give a fuller picture of time and cost performance. One caution: as work nears completion, SPI drifts toward 1.0 no matter how late it is, because Earned Value catches up with Planned Value once all the work is done. That's why SPI is most useful early and mid-execution, and is best read alongside the Critical Path.