Budgeted Cost for Work Scheduled (BCWS)
For the current period, BCWS represents the budgeted value of the work planned to be done in that period. On a cumulative to date basis, BCWS represents the sum of all the prior period budgets up through the status date. BCWS represents the amount of work that should be done if everything goes according to plan. The preposition in the name varies by source: the DoD EVM System Interpretation Guide writes Budgeted Cost for Work Scheduled, while NDIA's Planning & Scheduling Excellence Guide writes Budgeted Cost of Work Scheduled. Both name the same value; this encyclopedia follows the EVMSIG form.
Why it matters
BCWS is the baseline everything else gets measured against — it's what should be accomplished over time if everything goes according to plan.