Integrated Master Plan (IMP)
The IMP organizes a project around significant events rather than calendar dates, with accomplishments and completion criteria layered underneath each one. It's normally incorporated into the contract, making it contractually binding rather than just an internal planning tool. The IMP's events, accomplishments, and criteria are then carried down into the detailed schedule, the Integrated Master Schedule (IMS).
Why it matters
Because the IMP is event-driven rather than date-driven, it keeps a project focused on what must actually be accomplished before moving forward, not just on hitting a date on the calendar. That reduces the risk of declaring an event "done" prematurely just because a deadline arrived.