Milestone

Scheduling Terms Reviewed by forProject Technology - updated Sep 2026
Quick definition: A Milestone is a schedule event marking a significant accomplishment, deliverable, or the start or end of a project phase, rather than a task with duration.

Unlike tasks, a Milestone is a single point in time — it has zero duration and no resources assigned to it. Milestones are commonly used to flag key decision points, deliverables, or phase transitions in a schedule.

Why it matters

Milestones give a project team and stakeholders quick, high-visibility checkpoints for tracking progress without wading through every detailed task — they're often what gets reported upward in status reviews.

Also known as
N/A
Used in
Integrated Master Schedule; Weighted Milestone Method

FAQ

Does a Milestone have a duration?
No — a Milestone is a point in time with zero duration and no resources assigned.
What's the difference between a Milestone and an EV Milestone?
A Milestone marks a schedule-level event. An EV Milestone exists to measure earned value within a Work Package under the Weighted Milestone Method, and may not appear in the schedule at all.
Definition maintained by forProject Technology.