Milestone

Scheduling Terms Reviewed by forProject Technology - updated Sep 2026
Quick definition: A Milestone is a zero-Duration schedule event that marks a point in time, from a major deliverable or phase end to a detail point used to link Tasks in the schedule logic.

Unlike a Task, a Milestone has no resources assigned to it. Milestones can flag major events, such as decision points, deliverables, and phase transitions. They're also used at a detail level to connect Tasks, so the schedule logic reflects how the work really flows.

What this means for you

Milestones make events easy to track, from deliverables and phase transitions to the detail points that tie Tasks together. Tracking their forecast dates shows whether those events are on schedule.

Also known as
N/A
Used in
Integrated Master Schedule; Weighted Milestone Method

FAQ

Does a Milestone have a duration?
No. A Milestone is a point in time, with zero Duration and no resources assigned.
What's the difference between a Milestone and an EV Milestone?
A Milestone marks a schedule-level event. An EV Milestone exists to measure earned value within a Work Package under the Weighted Milestone Method, and may not appear in the schedule at all.
Definition maintained by forProject Technology.