B
Backward Pass
The Backward Pass is the schedule calculation that works back from the project finish date, following the links between tasks in reverse, to determine the latest each task can start and finish without delaying the project.
Scheduling Terms
Baseline Schedule
A Baseline Schedule is the approved version of a project schedule that serves as the standard against which ongoing schedule performance is measured.
Scheduling Terms
C
Constraint
In scheduling, a Constraint is an imposed or mandatory date placed on a specific task or milestone.
Scheduling Terms
Contract Milestone
A Contract Milestone is an event specifically named in a contract that represents a schedule commitment to complete a work task by a certain date.
Scheduling Terms
Critical Path
The Critical Path is the sequence of linked tasks that determines the project's finish date. Delay any task on it and the project finishes later. See also the Driving Path.
Scheduling Terms
Critical Path Analysis
Critical Path Analysis is the practice of identifying the Critical and Driving Paths in a schedule, confirming they are credible, and using them to judge where delay will do the most damage.
Scheduling Terms
Critical Path Method
(CPM)
Critical Path Method (CPM) is the scheduling calculation that turns task durations and their logical relationships into dates — determining when each task can start and finish, how much float each one has, and which sequence of tasks sets the project's finish date.
Scheduling Terms
Current Schedule
The Current Schedule is the most up-to-date version of a project's schedule, reflecting the latest plans, logic changes, and status updates.
Scheduling Terms
D
Driving Path
The Driving Path is the sequence of linked tasks that determines the completion date of a specific milestone or task, calculated the same way as the Critical Path but traced back from that milestone rather than from the project finish.
Scheduling Terms
Duration
Duration is the estimated time — in working days or portions of a day — needed to complete a task, based on a specific working calendar.
Scheduling Terms
Duration Percent Complete
Duration Percent Complete is the percentage of a task's planned Duration that has passed as of the status date, calculated as working days completed divided by total working days in the Duration.
Scheduling Terms
E
Early Finish Date
(EF)
The Early Finish Date is the earliest a task can finish: its Early Start Date advanced by the task's Duration across its working calendar.
Scheduling Terms
Early Start Date
(ES)
The Early Start Date is the earliest a task can begin, given its predecessor relationships — including their type and any lead or lag — and its working calendar.
Scheduling Terms
F
Float
Float (also called Slack) is the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Forecast Schedule
The Forecast Schedule is the working set of schedule values for every task — actual start, actual finish, and progress for work already performed, plus forecast dates and durations for work still remaining — updated each status cycle.
Scheduling Terms
Forward Pass
The Forward Pass is the schedule calculation that works forward from the project start date, following the links between tasks, to determine the earliest each task can start and finish.
Scheduling Terms
Free Float
Free Float (also called Free Slack) is the amount of time a task can be delayed without delaying the early start of its immediately following (successor) tasks.
Scheduling Terms
L
Lag
A Lag is a delay built into a logical relationship, holding the successor task back for a set amount of time after the predecessor condition is met.
Scheduling Terms
Late Finish Date
(LF)
The Late Finish Date is the latest a task can finish without delaying the project, given its successor relationships — including their type and any lead or lag — and its working calendar.
Scheduling Terms
Late Start Date
(LS)
The Late Start Date is the latest a task can start without delaying the project: its Late Finish Date less the task's Duration across its working calendar.
Scheduling Terms
Lead
A Lead is a planned overlap built into a logical relationship, allowing the successor task to start before the predecessor condition is fully met.
Scheduling Terms
N
Near Critical Path
A Near Critical Path is the second-longest (or third, fourth, and so on) sequence of linked tasks running to the project finish. It isn't driving the finish date today, but it's the likeliest candidate to become the Critical Path if conditions change.
Scheduling Terms
Negative Float
Negative Float (also called Negative Slack) occurs when Total Float in a schedule is a negative number, meaning there isn't enough time to finish a task within its imposed constraints.
Scheduling Terms
Network Schedule
A Network Schedule is a schedule format that shows tasks and milestones along with their logical dependencies (predecessors and successors).
Scheduling Terms
R
Relationship
A Relationship is the logical link between two schedule tasks that establishes the order in which they must occur, such as Finish-to-Start, Start-to-Start, Finish-to-Finish, or Start-to-Finish.
Scheduling Terms
Resource
A Resource is any personnel, material, equipment, service, or other cost needed to complete project work.
Scheduling Terms
S
Schedule Risk Assessment
(SRA)
A Schedule Risk Assessment (SRA) is a process that uses statistical or probabilistic techniques to identify and quantify technical, programmatic, and schedule risks affecting a program's schedule.
Scheduling Terms
Simulation
Simulation is a technique that uses random numbers and probability -- most commonly Monte Carlo simulation -- to test how uncertainty affects a schedule's reliability.
Scheduling Terms
T
Task
A Task, also called an Activity, is an element of work performed during a project, with its own expected duration, cost, and resource requirements.
Scheduling Terms
Total Float
Total Float (also called Total Slack) is the amount of time a task can be delayed from its early start without delaying the project finish date or any fixed constraint date.
Scheduling Terms