forProject's unified glossary of earned value, scheduling, and government-compliance terms — quick definitions, formulas, and how everything connects.

(click on a term to see details)

C
Constraint
In scheduling, a Constraint is an imposed or mandatory date placed on a specific task or milestone.
Scheduling Terms
Contract Milestone
A Contract Milestone is an event specifically named in a contract that represents a schedule commitment to complete a work task by a certain date.
Scheduling Terms
Critical Path
The Critical Path is the sequence of linked tasks that determines the project's finish date. Delay any task on it and the project finishes later. See also the Driving Path.
Scheduling Terms
Critical Path Analysis
Critical Path Analysis is the practice of identifying the Critical and Driving Paths in a schedule, confirming they are credible, and using them to judge where delay will do the most damage.
Scheduling Terms
Critical Path Method (CPM)
Critical Path Method (CPM) is the scheduling calculation that turns task durations and their logical relationships into dates — determining when each task can start and finish, how much float each one has, and which sequence of tasks sets the project's finish date.
Scheduling Terms
Current Schedule
The Current Schedule is the most up-to-date version of a project's schedule, reflecting the latest plans, logic changes, and status updates.
Scheduling Terms
F
Float
Float (also called Slack) is the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Forecast Schedule
The Forecast Schedule is the working set of schedule values for every task — actual start, actual finish, and progress for work already performed, plus forecast dates and durations for work still remaining — updated each status cycle.
Scheduling Terms
Forward Pass
The Forward Pass is the schedule calculation that works forward from the project start date, following the links between tasks, to determine the earliest each task can start and finish.
Scheduling Terms
Free Float
Free Float (also called Free Slack) is the amount of time a task can be delayed without delaying the early start of its immediately following (successor) tasks.
Scheduling Terms