forProject Encyclopedia

forProject's unified glossary of earned value, scheduling, and government-compliance terms — quick definitions, formulas, and how everything connects.

(click on a term to see details)

C
Constraint
In scheduling, a Constraint is a date limit placed on a task or milestone, such as "start no earlier than" or "finish no later than" a given date.
Scheduling Terms
Contract Milestone
A Contract Milestone is a type of Milestone that marks an event with contractual significance, such as a commitment in the contract to finish certain work by a certain date.
Scheduling Terms
Critical Path
The Critical Path is the sequence of linked tasks that determines the project's finish date. Delay any task on it and the project finishes later.
Scheduling Terms
Critical Path Analysis
Critical Path Analysis is another name for the Critical Path Method (CPM), the scheduling calculation that uses task Durations and logical relationships to work out each task's dates and Float and to find the Critical Path.
Scheduling Terms
Critical Path Length Index (CPLI)
The Critical Path Length Index (CPLI) measures how realistic the project's completion date is, based on the remaining length of the critical path and the total float available to the completion task.
Scheduling Terms
Critical Path Method (CPM)
Critical Path Method (CPM) is the scheduling calculation that turns task durations and their logical relationships into dates — determining when each task can start and finish, how much float each one has, and which sequence of tasks sets the project's finish date.
Scheduling Terms
D
DCMA 14-Point Assessment
The DCMA 14-Point Assessment is a set of 14 standard checks, developed by the Defense Contract Management Agency, for judging the health and quality of a project's Integrated Master Schedule.
Scheduling Terms
Driving Path
The Driving Path is the sequence of linked tasks that determines the completion date of a specific milestone or task, calculated the same way as the Critical Path but traced back from that milestone rather than from the project finish.
Scheduling Terms
Duration
Duration is the number of work periods — usually working days — that a task spans on its Working Calendar, not counting non-working periods such as weekends and holidays. Duration is not effort: a one-day task might involve one labor hour or a hundred.
Scheduling Terms
Duration Percent Complete
Duration Percent Complete is the percentage of a task's planned Duration that has passed as of the Status Date, calculated as Working Periods (e.g., Days) up through the Status Date divided by total Working Periods in the Duration.
Scheduling Terms
F
Float
Float (also called Slack) is the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Forecast Schedule
The Forecast Schedule is the working set of schedule values for every task — actual start, actual finish, and progress for work already performed, plus forecast dates and durations for work still remaining — updated each status cycle.
Scheduling Terms
Forward Pass
The Forward Pass is the Critical Path Method calculation that works forward from the project start date (or the status date, once work is underway) to find the earliest each task can start and finish.
Scheduling Terms
Free Float
Free Float (also called Free Slack) is the amount of time a task can be delayed without delaying the early start of its immediately following (successor) tasks.
Scheduling Terms
S
Schedule
A Schedule is a plan that shows when specified work will be performed to meet project objectives on time.
Scheduling Terms
Schedule Risk Assessment (SRA)
A Schedule Risk Assessment (SRA) is a process that uses statistical or probabilistic techniques to identify and quantify technical, programmatic, and schedule risks affecting a project's schedule.
Scheduling Terms
Schedule Visibility Task (SVT)
A Schedule Visibility Task (SVT) is a task with no resources, shown in the schedule for visibility only, that represents work or waiting that affects the project but isn't part of its Performance Measurement Baseline (PMB).
Scheduling Terms
Simulation
Simulation is a technique that uses random numbers and probability — most commonly Monte Carlo simulation — to test how uncertainty affects a schedule's reliability.
Scheduling Terms
Slack
Slack is another name for Float — the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Soft Constraint
A Soft Constraint is a Constraint that guides when a task or milestone is scheduled, such as how early it can start or finish, without inhibiting the logical flow of the schedule.
Scheduling Terms