Horizontal Schedule Integration
Horizontal integration focuses on how Work Packages, Planning Packages, and lower-level tasks connect to one another through dependencies and constraints — including "hand-offs" of products between different Integrated Product Teams. This logical linking lets a schedule show how a delay in one task will ripple forward into the tasks and milestones that depend on it.
Why it matters
Without horizontal integration, a schedule is just a list of dates rather than a true network schedule — it can't show how a slip in one area will actually impact downstream work. Because it captures these cross-team hand-offs and dependencies, it's essential for realistically forecasting schedule impacts across an Integrated Master Schedule.