Driving Path
A Driving Path is calculated like the Critical Path, but traced back from an interim milestone or task instead of from the project finish. It is the longest chain of linked tasks leading to that milestone, so its tasks are the ones keeping the milestone from finishing any sooner. It answers the question, "What is actually holding this date?" A project can have many Driving Paths, one for every milestone worth managing.
What this means for you
A Driving Path shows what is setting the date of a milestone the team or customer cares about, such as a delivery, a test event, or a phase gate. Critical Path Analysis won't show this unless that milestone happens to sit on the Critical Path. Because an interim milestone can slip while the finish date holds, the Driving Path is often the earliest warning that a commitment is at risk.