Driving Path
A Driving Path is calculated exactly like the Critical Path, but traced back from an interim milestone or task rather than from the project finish. It is the longest continuous chain of tasks leading to that milestone — other chains reaching the same point are shorter and therefore have slack. Its tasks are the ones preventing that milestone from completing any sooner, which makes it the answer to "what is actually holding this date?" In practice it is identified by tracing the chain of predecessor and successor relationships that drive the milestone's date. Like the Critical Path, it normally runs back to Time Now, though it can begin later if the driver originates from a constrained input. A project can have many Driving Paths — one for every milestone worth managing.
Why it matters
A Driving Path reveals what is determining the date of a milestone the team or the customer cares about — a delivery, a test event, or a phase gate — which Critical Path analysis will not surface unless that milestone happens to sit on the Critical Path. Because an interim milestone can slip while the project's finish date holds steady, the Driving Path is often the earliest indication that a commitment is at risk. Both analyses are normally run together: the Critical Path to the project end, and Driving Paths to the key milestones along the way.
See also
FAQ
© 2026 forProject Technology, Inc.