Forecast Schedule
The Baseline Schedule is the approved plan that performance is measured against. The Forecast Schedule is everything the schedule currently says about each task: actual dates and progress for work already performed, and forecast dates and remaining Duration for work still ahead. Despite the name, it combines what actually happened with what is now expected. Comparing it against the baseline shows where the schedule has slipped.
What this means for you
The Forecast Schedule is what the team actually works to, because it reflects both what has happened and what is now expected rather than the original plan. It is the predictive half of the pair: the baseline states what was committed, and the forecast states where the project stands and where it is heading. A forecast that is not kept current with status, approved scope changes, and workarounds stops being a useful management tool.