Over Target Schedule (OTS)
When a project slips far enough that the baseline dates are no longer achievable, measuring performance against them stops telling anyone anything useful. An OTS resets those dates to something realistic so the numbers mean something again. It comes out of Formal Reprogramming — the same process that produces an Over Target Baseline on the cost side — and it takes formal approval and a documented Baseline Change Request, not just a decision by the project team. The contract itself doesn't move: delivery dates, terms, and conditions all stay as they were, and only the internal measurement dates change.
Why it matters
An OTS lets a project keep meaningful schedule performance metrics even after the original dates have slipped, rather than measuring against a schedule everyone knows is no longer realistic.
See also
FAQ
© 2026 forProject Technology, Inc.
