Duration Percent Complete
For example, if 5 of a task's 10 working days have passed at the status date, Duration Percent Complete is 50% — regardless of how much work has actually been accomplished. It is measured against the task's working calendar, so non-working days do not count. This makes it a time-based measure, distinct from Physical Percent Complete, which assesses actual accomplishment.
Why it matters
Duration Percent Complete is useful for Critical Path scheduling status, but it can be misleading for earned value purposes, since time passing doesn't guarantee proportional physical progress. It is also the figure most scheduling tools report by default, which is why it gets mistaken for a progress measure.