Contract Performance Report (CPR)
The five CPR formats cover cost/schedule performance by WBS (Format 1), cost/schedule performance by OBS (Format 2), baseline changes (Format 3), staffing (Format 4), and variance explanations and problem analysis (Format 5). Together, they give the customer a structured view of EVM data rather than a single summary number. These reports were superseded by the IPMR and IPMDAR reports.
Why it matters
The CPR is how a customer got standardized, comparable EVM data across different contracts and contractors, rather than each project reporting performance its own way. It is sometimes referenced in EVM discussions even as most current DoD contracts have moved to newer report formats such as the IPMR and IPMDAR.