Schedule Visibility Task (SVT)
SVTs make outside dependencies visible in the schedule logic instead of hiding them in a Lag or a constrained milestone. Typical uses are work performed by an outside organization such as the customer, work funded through capital or another contract, and wait time when nobody is working. Because an SVT is a real task, it can be updated, tracked, and seen on the Critical Path, which a Lag can't. An SVT sits outside the Performance Measurement Baseline (PMB), so it shouldn't be used for subcontractor work or for in-scope work that simply hasn't had resources assigned.
What this means for you
Work outside the project's control still drives its dates. A customer review hidden in a 20-day Lag goes unwatched until it slips, but the same review modeled as an SVT can be tracked, reported, and escalated like any other task.