The formulas and acronyms every earned value practitioner reaches for, on one page. It’s the same content as our laminated Earned Value Quick Reference card, which we’ve handed out at industry events for years. Each item links to its full definition in the forProject Encyclopedia.

Free download: Download the two-page PDF card (3.5 × 7.75 in, formulas on the front, acronyms on the back). Free to print for training and reference.

Earned Value Formulas

Cost & Schedule Variances

Cost Variance (CV) CV = BCWP − ACWP
Schedule Variance (SV) SV = BCWP − BCWS
Cost Variance % (CV%) CV% = (BCWP − ACWP) ÷ BCWP × 100
Schedule Variance % (SV%) SV% = (BCWP − BCWS) ÷ BCWS × 100

Performance Indices & Percentages

Cost Performance Index (CPI) CPI = BCWP ÷ ACWP
Schedule Performance Index (SPI) SPI = BCWP ÷ BCWS
TCPI (BAC) TCPIBAC = (BAC − BCWP) ÷ (BAC − ACWP)
TCPI (EAC) TCPIEAC = (BAC − BCWP) ÷ (EAC − ACWP)
Percent Complete % Complete = BCWP ÷ BAC × 100
Percent Scheduled % Scheduled = BCWS ÷ BAC × 100
Percent Spent (BAC) % SpentBAC = ACWP ÷ BAC × 100
Percent Spent (EAC) % SpentEAC = ACWP ÷ EAC × 100

At-Completion Values

Estimate at Completion (EAC) EAC = ACWP + ETC
Estimate to Complete (ETC) ETC = EAC − ACWP
Variance at Completion (VAC) VAC = BAC − EAC

Independent EACs

IEAC (CPI) IEACCPI = BAC ÷ CPI
IEAC (3-month average CPI) IEAC3-Mo Avg = ACWP + (BAC − BCWP) ÷ CPI3-Mo Avg
IEAC (CPI × SPI) IEACCPI×SPI = ACWP + (BAC − BCWP) ÷ (CPI × SPI)

Earned Value Acronyms

ACWP Actual Cost of Work Performed
AE Apportioned Effort
AUW Authorized Unpriced Work
BAC Budget at Completion
BCWP Budgeted Cost for Work Performed
BCWS Budgeted Cost for Work Scheduled
CA Control Account
CAM Control Account Manager
CAP Control Account Plan
CBB Contract Budget Base
CPI Cost Performance Index
CTC Contract Target Cost
CV Cost Variance
EAC Estimate at Completion
EOC Elements of Cost
ETC Estimate to Complete
G&A General & Administrative
IBR Integrated Baseline Review
IEAC Independent Estimate at Completion
IMP Integrated Master Plan
IMS Integrated Master Schedule
IPMDAR Integrated Program Management Data & Analysis Report
IPMR Integrated Program Management Report
IPT Integrated Product Team
LOE Level of Effort
MR Management Reserve
NCC Negotiated Contract Cost
OBS Organizational Breakdown Structure
ODC Other Direct Cost
OTB Over Target Baseline
OTS Over Target Schedule
PMB Performance Measurement Baseline
PP Planning Package
QBD Quantifiable Backup Data
RAM Responsibility Assignment Matrix
SLPP Summary Level Planning Package
SPI Schedule Performance Index
SRA Schedule Risk Assessment
SV Schedule Variance
TAB Total Allocated Budget
TCPI To Complete Performance Index
UB Undistributed Budget
VAC Variance at Completion
VAR Variance Analysis Report
WBS Work Breakdown Structure
WP Work Package

Want the software that does these calculations for you? See EVMS forProject, our EVM and EVMS software for Microsoft Project and Primavera P6.