forProject Encyclopedia

forProject's unified glossary of earned value, scheduling, and government-compliance terms — quick definitions, formulas, and how everything connects.

(click on a term to see details)

A
Accrual
An Accrual is the recording of actual costs for work that has been performed but not yet paid for. Sometimes called "Estimated Actual Costs."
EVM Terms
Activity
An Activity, also called a Task, is a measurable, discrete unit of work with a clear start and end. It's the basic building block of a project schedule, and activities are sequenced and linked together to build the overall schedule.
Scheduling Terms
Actual Cost
Actual Cost is another name for Actual Cost of Work Performed (ACWP) — the real cost incurred for work completed in a given period.
EVM Terms
Actual Cost of Work Performed (ACWP)
Actual Cost of Work Performed (ACWP) is the cost incurred and recorded in accomplishing the work performed within a given time period, including all recorded incurred costs plus estimated actuals.
EVM Terms
Applied Direct Costs (ADC)
Applied Direct Costs are the actual direct costs of labor, material, and other resources, recognized in the period they're used rather than when they're paid for.
EVM Terms
Apportioned Effort (AE)
Apportioned Effort is an Earned Value measurement method that is applied in cases where accomplishment is measured in relation to a related, directly measurable task.
EVM Terms
Authorization to Proceed (ATP)
Authorization to Proceed (ATP) is the official go-ahead for a contractor to begin work, typically issued by the procuring contracting officer.
EVM Terms
Authorized Unpriced Work (AUW)
Authorized Unpriced Work (AUW) is new work scope the customer has formally authorized and had estimated, but hasn't yet negotiated a price for.
EVM Terms
Authorized Work
Authorized Work is the work scope on a contract or project that management has formally authorized to be performed.
EVM Terms
B
Backward Pass
The Backward Pass is the schedule calculation that works back from the project finish date, following the links between tasks in reverse, to determine the latest each task can start and finish without delaying the project.
Scheduling Terms
Baseline
In EVMS, "Baseline" refers to the approved plan — cost, schedule, and technical scope together — against which a project's cost and schedule performance is measured throughout its life.
EVM Terms
Baseline Change Control
Baseline Change Control is the formal process used to establish, record, analyze, and communicate approved changes to the Baseline Plan.
EVM Terms
Baseline Change Request (BCR)
A Baseline Change Request (BCR) is the formal document that proposes a change to the baseline, along with its justification and its impact on scope, cost, and schedule.
EVM Terms
Baseline Plan
The Baseline Plan is the approved, integrated cost, schedule, and technical plan for a project, used as the standard for measuring performance.
EVM Terms
Baseline Schedule
A Baseline Schedule is the approved version of a project schedule that serves as the standard against which ongoing schedule performance is measured.
Scheduling Terms
Basis of Estimate (BOE)
A Basis of Estimate (BOE) is the documented rationale behind a cost or resource estimate for a specific piece of project scope.
EVM Terms
Bill of Material (BOM)
A Bill of Material (BOM) is a listing of all the material items required to produce a single unit of a product.
EVM Terms
Budget
In EVMS, a Budget is the approved resource estimate for performing a defined scope of work within the established schedule baseline. Budgets at various levels roll up into the project's overall Budget at Completion (BAC), and when time-phased the budget is referred to as BCWS.
EVM Terms
Budget at Completion (BAC)
Budget at Completion (BAC) is the total authorized budget for accomplishing all of the defined work in a project or a sub-element of a project such as WBS Element, Control Account, Work Package, or Planning Package.
EVM Terms
Budgeted Cost for Work Performed (BCWP)
Budgeted Cost for Work Performed (BCWP), also called Earned Value, is the budgeted value of the work actually accomplished on a project. It may be measured for a specific period or cumulative to date.
EVM Terms
Budgeted Cost for Work Scheduled (BCWS)
Budgeted Cost for Work Scheduled (BCWS), also called Planned Value, is the time-phased distribution of budget for any project element based on the work that is scheduled to be accomplished over time.
EVM Terms
C
Charge Number
A Charge Number is a generic name for the authorization code for a specific piece of work, at the lowest level tracked, to which a performing organization charges labor, materials, and other project costs.
EVM Terms
Cognizant Federal Agency (CFA)
The Cognizant Federal Agency (CFA) is the government agency responsible for determining whether a contractor's Earned Value Management System complies with the EIA-748 guidelines.
Government Standards
Constraint
In scheduling, a Constraint is an imposed or mandatory date placed on a specific task or milestone.
Scheduling Terms
Contract Budget Base (CBB)
The Contract Budget Base (CBB) is the Negotiated Contract Cost plus the estimated cost of any Authorized Unpriced Work — the total budget authorized under the contract.
EVM Terms
Contract Data Requirements List (CDRL)
A Contract Data Requirements List (CDRL) is the part of a contract that specifies exactly what data items a contractor must deliver, and when.
Government Standards
Contract Funds Status Report (CFSR)
The Contract Funds Status Report (CFSR) is a Department of Defense report used to track and forecast the funding needed to complete a contract.
Government Standards
Contract Line Item Number (CLIN)
A Contract Line Item Number (CLIN) is a unique identifier assigned to specific items or services listed within a contract, used for administration, accounting, billing, and deliverable tracking.
Government Standards
Contract Management Office (CMO)
The Contract Management Office (CMO) is the Government organization responsible for ensuring a contractor complies with the terms and conditions of its contract.
Government Standards
Contract Milestone
A Contract Milestone is an event specifically named in a contract that represents a schedule commitment to complete a work task by a certain date.
Scheduling Terms
Contract Performance Report (CPR)
The Contract Performance Report (CPR), formerly called the Cost Performance Report, is a set of up to five standardized report formats used to show a contract's cost and schedule performance in earned value terms. This term and these reports are obsolete and no longer in common use.
Government Standards
Contract Target Cost (CTC)
Contract Target Cost (CTC), also called Negotiated Contract Cost, is the negotiated cost of the original contract plus all definitized contractual changes, excluding any authorized but unpriced changes.
EVM Terms
Contract Target Price (CTP)
Contract Target Price (CTP), for Government contracts, is the negotiated contract cost plus the target profit or fee.
EVM Terms
Contract Type
Contract Type refers to the various forms a contract can take for acquiring goods or services, such as Cost Plus Fixed Fee, Cost Plus Incentive Fee, Firm Fixed Price, Fixed Price Incentive Fee, or Unit Price.
EVM Terms
Contract Work Breakdown Structure (CWBS)
The Contract Work Breakdown Structure (CWBS) is the product-oriented breakdown of a specific Government contract's work, developed in line with MIL-HDBK-881 and the contract's Statement of Work.
Government Standards
Control Account (CA)
A Control Account (CA) is the key management point where scope, schedule, cost, and risk are managed together, and where Earned Value data is typically collected.
EVM Terms
Control Account Manager (CAM)
The Control Account Manager (CAM) is the individual directly responsible for managing a Control Account, including its scope, schedule, cost, and technical performance.
EVM Terms
Control Account Plan (CAP)
A Control Account Plan (CAP) is a document or electronic plan that compiles a Control Account's scope, schedule, and budget information into a single, integrated plan of performance.
EVM Terms
Cost Performance Index (CPI)
Cost Performance Index (CPI) is a measure of cost efficiency, calculated as the ratio of earned value (BCWP) to actual cost (ACWP). CPI can be calculated both for the current period and cumulative to date.
EVM Terms
Cost Variance (CV)
Cost Variance (CV) is the difference between earned value (BCWP) and actual cost (ACWP), and is a measure of cost efficiency. CV can be calculated both for the current period and cumulative to date.
EVM Terms
Cost/Schedule Status Report (C/SSR)
The Cost/Schedule Status Report (C/SSR) is an obsolete, simplified EVM report format once used to provide basic cost and schedule status on smaller government contracts.
Government Standards
Critical Path
The Critical Path is the sequence of linked tasks that determines the project's finish date. Delay any task on it and the project finishes later. See also the Driving Path.
Scheduling Terms
Critical Path Analysis
Critical Path Analysis is the practice of identifying the Critical and Driving Paths in a schedule, confirming they are credible, and using them to judge where delay will do the most damage.
Scheduling Terms
Critical Path Method (CPM)
Critical Path Method (CPM) is the scheduling calculation that turns task durations and their logical relationships into dates — determining when each task can start and finish, how much float each one has, and which sequence of tasks sets the project's finish date.
Scheduling Terms
Current Schedule
The Current Schedule is the most up-to-date version of a project's schedule, reflecting the latest plans, logic changes, and status updates.
Scheduling Terms
D
Defense Contract Audit Agency (DCAA)
The Defense Contract Audit Agency (DCAA) is the U.S. Department of Defense agency responsible for performing contract audits and providing financial advisory services related to DoD contracts.
Government Standards
Defense Contract Management Agency (DCMA)
The Defense Contract Management Agency (DCMA) is the Department of Defense component that works directly with contractors to ensure supplies and services are delivered on time, within cost, and to required performance standards.
Government Standards
Direct Costs
Direct Costs are costs that can be specifically identified with a particular contract or project and are charged to it directly — for example materials, labor, subcontractor charges, or other direct costs such as travel.
EVM Terms
Discrete Effort
Discrete Effort is a classification that identifies work that will earn value based on objective or measurable outputs or work products.
EVM Terms
Discrete Milestone Method
The Discrete Milestone Method is a way of applying the Weighted Milestone Method in which each milestone is all or nothing — its full weight is earned when it's complete, and nothing is earned before.
EVM Terms
Distributed Budget
Distributed Budget is the sum of the budgets, direct and indirect, that have been allocated to Control Accounts and Summary Level Planning Packages through the Control Account planning and Work Authorization process.
EVM Terms
Driving Path
The Driving Path is the sequence of linked tasks that determines the completion date of a specific milestone or task, calculated the same way as the Critical Path but traced back from that milestone rather than from the project finish.
Scheduling Terms
Duration
Duration is the estimated time — in working days or portions of a day — needed to complete a task, based on a specific working calendar.
Scheduling Terms
Duration Percent Complete
Duration Percent Complete is the percentage of a task's planned Duration that has passed as of the status date, calculated as working days completed divided by total working days in the Duration.
Scheduling Terms
E
Early Finish Date (EF)
The Early Finish Date is the earliest a task can finish: its Early Start Date advanced by the task's Duration across its working calendar.
Scheduling Terms
Early Start Date (ES)
The Early Start Date is the earliest a task can begin, given its predecessor relationships — including their type and any lead or lag — and its working calendar.
Scheduling Terms
Earned Standards Complete Method
The Earned Standards Complete Method is an earned value technique that credits progress based on accomplishment of pre-established labor-hour standards for each unit of work completed.
EVM Terms
Earned Value (EV)
Earned Value (EV) is another name for Budgeted Cost for Work Performed (BCWP) — the value of work actually completed, expressed in terms of its original budget.
EVM Terms
Earned Value Management (EVM)
Earned Value Management (EVM) is a management approach that integrates a project's scope, schedule, and cost to give objective, data-driven performance measurement and more realistic forecasting.
EVM Terms
Earned Value Management System (EVMS)
An Earned Value Management System (EVMS) is the combination of processes, people, and information and tools that enables an organization to practice effective Earned Value Management.
EVM Terms
Earned Value Method
An Earned Value Method (EV Method) is the specific technique chosen in advance to measure how much earned value (BCWP) a Work Package has achieved as work progresses.
EVM Terms
Elements of Cost (EOC)
Elements of Cost (EOC) are the major categories — such as labor, material, subcontract, and overhead — into which a project's direct and indirect costs are planned and recorded.
EVM Terms
Equivalent Units Method
The Equivalent Units Method is an earned value technique that credits partial progress on a unit of work, not just fully completed units.
EVM Terms
Estimate at Completion (EAC)
Estimate at Completion (EAC) is the projected total cost of all authorized work, equal to actual costs incurred to date plus the estimated cost to complete the remaining work.
EVM Terms
Estimate to Complete (ETC)
Estimate to Complete (ETC) is the projected cost of finishing all remaining authorized work from this point forward.
EVM Terms
Estimated Actual Costs
Estimated Actual Costs are reasonable estimates of costs already incurred for completed work that haven't yet been posted in the formal accounting system.
EVM Terms
EV Management Implementation Guide (EVMIG)
The EV Management Implementation Guide (EVMIG) is the Department of Defense's central guidance document for implementing and overseeing Earned Value Management on DoD contracts.
Government Standards
EV Milestone
An EV Milestone is a subdivision of a Work Package, defined so that earned value can be measured at a finer level than the Work Package as a whole.
EVM Terms
EVMS Guidelines
The EVMS Guidelines are the 27 standard requirements, established under ANSI/EIA-748-E, that define what a compliant Earned Value Management System must do.
Government Standards
EVMS Interpretation Guide (EVMSIG)
The EVMS Interpretation Guide (EVMSIG) is the Department of Defense's authoritative interpretation of the EIA-748 guidelines, and the basis on which DoD assesses whether a contractor's Earned Value Management System complies.
Government Standards
Exhibit Line Item Number (ELIN)
An Exhibit Line Item Number (ELIN) is an identifier used on a government contract to provide additional detail about a deliverable beyond what's captured in the standard Contract Line Item Number (CLIN) or Sub Line Item Number (SLIN).
Government Standards
F
Float
Float (also called Slack) is the amount of time a task can be delayed before it affects other tasks or the project's finish date.
Scheduling Terms
Forecast Schedule
The Forecast Schedule is the working set of schedule values for every task — actual start, actual finish, and progress for work already performed, plus forecast dates and durations for work still remaining — updated each status cycle.
Scheduling Terms
Formal Reprogramming
Formal Reprogramming is a comprehensive re-plan of the remaining contract effort that results in a Total Allocated Budget exceeding the current Contract Budget Base.
Government Standards
Forward Pass
The Forward Pass is the schedule calculation that works forward from the project start date, following the links between tasks, to determine the earliest each task can start and finish.
Scheduling Terms
Forward Pricing Rates Agreement (FPRA)
A Forward Pricing Rates Agreement (FPRA) is a formal bilateral agreement in which the government agrees to accept a contractor's negotiated rates for use in pricing and negotiating future proposals.
Government Standards
Forward Pricing Rates Brochure (FPRB)
A Forward Pricing Rates Brochure (FPRB) is a document summarizing the Forward Pricing Rates Agreements currently in effect between a contractor and its U.S. Government customers.
Government Standards
Free Float
Free Float (also called Free Slack) is the amount of time a task can be delayed without delaying the early start of its immediately following (successor) tasks.
Scheduling Terms
I
In-Scope Change
An In-Scope Change is a baseline change that falls within the existing scope of a contract and therefore doesn't require a formal contract modification.
EVM Terms
Independent Estimate at Completion (IEAC)
An Independent Estimate at Completion (IEAC) is a cost forecast calculated using a standard formula based on past performance, used to sanity-check the manager's own Estimate at Completion.
EVM Terms
Indirect Costs
Indirect Costs are costs incurred for common or shared business objectives that can't be traced to a single specific contract or project.
EVM Terms
Integrated Baseline Review (IBR)
An Integrated Baseline Review (IBR) is a joint government/contractor review held to confirm that a project's Performance Measurement Baseline (PMB) is realistic and complete.
Government Standards
Integrated Master Plan (IMP)
The Integrated Master Plan (IMP) is an event-based project plan made up of a hierarchy of events, each supported by specific accomplishments, and each accomplishment tied to criteria that must be met to consider it complete.
EVM Terms
Integrated Master Schedule (IMS)
The Integrated Master Schedule (IMS) is a detailed, networked schedule containing all the Work Packages, Planning Packages, and lower-level tasks needed to support a project's events, accomplishments, and criteria.
EVM Terms
Integrated Product Team (IPT)
An Integrated Product Team (IPT) is a multidisciplinary team given management responsibility for one or more elements of a project.
EVM Terms
Integrated Program Management Data and Analysis Report (IPMDAR)
The Integrated Program Management Data and Analysis Report (IPMDAR) is a US Government contract report that reflects current and forecast contract cost and schedule performance. It is issued under data item description DI-MGMT-81861, currently at revision C.
Government Standards
Integrated Program Management Report (IPMR)
The Integrated Program Management Report (IPMR) is a set of standardized reports required on many US Government contracts with a formal Earned Value Management requirement.
Government Standards
Integrated Risk Assessment (IRA)
An Integrated Risk Assessment (IRA) is an analysis that combines a program's separate technical, schedule, and cost risk assessments into a single probabilistic view of overall program cost.
EVM Terms
Internal Re-planning
Internal Re-planning is any change to a project's budgets that stays within the existing contract scope and within the approved budget ceiling.
EVM Terms
IPT Leader
An IPT Leader is the individual identified as responsible for an Integrated Product Team (IPT).
EVM Terms
L
Lag
A Lag is a delay built into a logical relationship, holding the successor task back for a set amount of time after the predecessor condition is met.
Scheduling Terms
Late Finish Date (LF)
The Late Finish Date is the latest a task can finish without delaying the project, given its successor relationships — including their type and any lead or lag — and its working calendar.
Scheduling Terms
Late Start Date (LS)
The Late Start Date is the latest a task can start without delaying the project: its Late Finish Date less the task's Duration across its working calendar.
Scheduling Terms
Latest Revised Estimate (LRE)
The Latest Revised Estimate (LRE) is a Control Account Manager's most current estimate of cost at completion, broken out by element of cost, for a given Control Account, as approved by the Program Manager.
EVM Terms
Lead
A Lead is a planned overlap built into a logical relationship, allowing the successor task to start before the predecessor condition is fully met.
Scheduling Terms
Level of Effort (LOE)
Level of Effort (LOE) is work of a general or supportive nature — such as supervision or contract administration — that doesn't produce a definite end product.
EVM Terms
M
Management Reserve (MR)
Management Reserve (MR) is budget held in reserve for unknown but in-scope effort — work that will be needed but cannot be identified in advance.
EVM Terms
Master Budget Log
The Master Budget Log is a document that tracks how a project's performance budgets have been distributed over its life, including changes to Control Accounts, Undistributed Budget, and Management Reserve.
EVM Terms
Measured Milestone
Measured Milestone is a way of applying the Weighted Milestone Method in which partial progress can be claimed within a milestone, rather than waiting for it to be fully complete.
EVM Terms
Milestone
A Milestone is a schedule event marking a significant accomplishment, deliverable, or the start or end of a project phase, rather than a task with duration.
Scheduling Terms
Milestone Method
The Milestone Method is an earned value technique that breaks a discrete Work Package into several weighted milestones, each representing a portion of the Work Package's overall scope and budget.
EVM Terms
N
Near Critical Path
A Near Critical Path is the second-longest (or third, fourth, and so on) sequence of linked tasks running to the project finish. It isn't driving the finish date today, but it's the likeliest candidate to become the Critical Path if conditions change.
Scheduling Terms
Negative Float
Negative Float (also called Negative Slack) occurs when Total Float in a schedule is a negative number, meaning there isn't enough time to finish a task within its imposed constraints.
Scheduling Terms
Negotiated Contract Cost (NCC)
Negotiated Contract Cost (NCC) is the negotiated cost of the original contract plus all negotiated contractual changes, not counting any authorized but unpriced work.
EVM Terms
Network Schedule
A Network Schedule is a schedule format that shows tasks and milestones along with their logical dependencies (predecessors and successors).
Scheduling Terms
O
Organizational Breakdown Structure (OBS)
The Organizational Breakdown Structure (OBS) is the organizational structure — including major subcontractors — responsible for accomplishing a project's authorized work.
EVM Terms
Other Direct Cost (ODC)
Other Direct Costs (ODC) are costs charged directly to a project that don't fall under the main direct cost categories of labor or material.
EVM Terms
Out-of-Scope Change
An Out-of-Scope Change is a baseline change that falls outside the existing contract's scope, meaning it requires a formal contractual change to implement.
EVM Terms
Over Target Baseline (OTB)
An Over Target Baseline (OTB) is the condition that exists when a project's Total Allocated Budget exceeds its Contract Budget Base.
Government Standards
Over Target Schedule (OTS)
An Over Target Schedule (OTS) is a project schedule that has been formally reprogrammed so that work, and the budgets time-phased against it, extend beyond the contract's milestones or completion date.
Government Standards
Overhead
Overhead is a category of Indirect Cost covering shared costs that support a particular function, facility, or business unit rather than any single project.
EVM Terms
P
Percent Complete
Percent Complete is a general measure of progress on a task or Work Package, expressed in various ways depending on what's being measured.
EVM Terms
Percent Complete (EV Method)
Percent Complete (EV Method) is an earned value technique in which a Work Package earns credit based on an assessment of how much of its work is complete.
EVM Terms
Percent Spent
Percent Spent measures how much has been spent on a task so far compared to its total expected cost.
EVM Terms
Performance Measurement Baseline (PMB)
The Performance Measurement Baseline (PMB) is the time-phased baseline budget against which Control Account performance is measured. It is the sum of all budgets, both direct and indirect, that have been allocated to Control Account and Summary Level Planning Package elements, plus the amount temporarily held in Undistributed Budget.
EVM Terms
Performing Organization
The Performing Organization is the organizational unit — typically a functional department or group — that applies resources to actually carry out a Work Package.
EVM Terms
Physical Percent Complete
Physical Percent Complete is the assessed progress of actual work accomplished on a task, independent of the passage of time against its schedule.
EVM Terms
Planned Value (PV)
Planned Value (PV) is the time-phased budget for the work scheduled to be performed — the same figure as Budgeted Cost for Work Scheduled (BCWS).
EVM Terms
Planning & Scheduling Excellence Guide (PASEG)
The Planning & Scheduling Excellence Guide (PASEG) is the NDIA Integrated Program Management Division's reference guide on building, using, and maintaining an Integrated Master Schedule.
Government Standards
Planning Package
A Planning Package is a future portion of work within a Control Account that hasn't yet been broken down into detailed Work Packages.
EVM Terms
Program Manager (PM)
The Program Manager (PM) is the individual with overall responsibility for the cost, schedule, and technical performance of a program, including the budgets and baseline changes authorized within it.
EVM Terms
Project Milestone
A Project Milestone is a project-level milestone marking a significant event, a major deliverable, or the start or end of a major project phase.
Scheduling Terms
S
Schedule
EVM Terms
Schedule Performance Index
EVM Terms
Schedule Risk Assessment (SRA)
A Schedule Risk Assessment (SRA) is a process that uses statistical or probabilistic techniques to identify and quantify technical, programmatic, and schedule risks affecting a program's schedule.
Scheduling Terms
Schedule Variance (SV)
Schedule Variance (SV) is the difference between earned value (BCWP) and planned value (BCWS), calculated as SV = BCWP - BCWS.
EVM Terms
Simulation
Simulation is a technique that uses random numbers and probability -- most commonly Monte Carlo simulation -- to test how uncertainty affects a schedule's reliability.
Scheduling Terms
Slack
EVM Terms
Start/Finish Method
EVM Terms
Statement of Work (SOW)
A Statement of Work (SOW) is the document that defines the work scope of a program, project, or a specific element such as a WBS element, Control Account, or Work Package.
EVM Terms
Summary Level Planning Package (SLPP)
A Summary Level Planning Package (SLPP) is an element that represent far-term work that under a summary WBS element that is not yet practical to break into detail Control Accounts and Work Packages.
EVM Terms
Surveillance
Surveillance is the recurring, independent review process -- typically performed by the Defense Contract Management Agency (DCMA) -- that checks a company's EVM system for continuing compliance with ANSI/EIA-748 and its own written system documentation.
Government Standards
V
Validation
Validation is the formal recognition by an independent party that a company's Earned Value Management System (EVMS) meets the guidelines of ANSI/EIA-748.
EVM Terms
Validation Review (VR)
A Validation Review (VR) is a formal Government review, conducted at a contractor's facility, to assess whether the contractor's proposed EVMS complies with ANSI/EIA-748.
Government Standards
Variance Analysis Report (VAR)
A Variance Analysis Report (VAR) identifies significant cost and schedule variances on a project, along with their size, causes, immediate impact, and planned corrective actions.
Government Standards
Variance Analysis Thresholds
Variance Analysis Thresholds are the dollar-amount and percentage criteria, set by the Project Manager, that determine when a Control Account Manager must complete a Variance Analysis Report.
EVM Terms
Variance at Completion (VAC)
Variance at Completion (VAC) is the difference between the Budget at Completion (BAC) and the current approved Estimate at Completion (EAC), showing whether a project is expected to finish over or under budget.
EVM Terms
Vertical Schedule Integration
Vertical Schedule Integration is the practice of tying higher-level summary schedules to lower-level, detailed schedules so that data is consistent across all levels of the project's schedule hierarchy.
EVM Terms
W
WBS Dictionary
The WBS Dictionary is a document that gives a brief narrative definition of each element of the Work Breakdown Structure, describing its work scope and deliverables.
EVM Terms
WBS Element Manager
A WBS Element Manager is the individual assigned responsibility for accomplishing the work identified for a summary-level WBS element, above the Control Account level.
EVM Terms
Weighted Milestone Method
The Weighted Milestone Method is an Earned Value technique in which Work Package Milestones are defined, with earned value credited on a discrete (0/100) basis as each milestone is completed.
EVM Terms
Work Authorization (WA)
A Work Authorization (WA) is the document that formally assigns responsibility and authority for a defined element of work, within a specified schedule, budget, and Statement of Work.
EVM Terms
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) is a product-oriented, hierarchical breakdown of all the work to be performed on a project, organizing hardware, software, services, and other deliverables into a single unifying structure.
EVM Terms
Work Package (WP)
A Work Package (WP) is a natural subdivision of the tasks or activities within a Control Account, and the point at which work is planned, progress is measured, and earned value is computed.
EVM Terms